Supervisors vote Tuesday on $24.3 million more for the Prince William Parkway interchange at Minnieville Road. Completion would slip to Aug. 30, 2028.
The new interchange at Prince William Parkway and Minnieville Road needs $24.3 million more and will finish five months later than planned, according to a Prince William County staff report.
The Board of County Supervisors takes up the request Tuesday, Dec. 1. It is item 7-G on the Dec. 1 agenda, listed among the public hearings.
The interchange is in Dale City, about three miles west of Lake Ridge. Prince William Parkway also runs through Lake Ridge, so the work is on a road many residents use.
Why the cost went up
The project will carry Prince William Parkway under Minnieville Road at a single-point urban interchange. Supervisors awarded a $61,406,701 construction contract to Lane Construction Corp. on Nov. 18, 2025, the staff report says.
The bid plans called for a soil-nail retaining wall. After the contract was awarded, the Virginia Department of Transportation raised concerns about variable soil conditions in the area. The report says those concerns made the original wall design “not feasible and impractical.”
The county switched to a post-and-panel wall with tiebacks and steel plate lagging, which VDOT has approved. Staff wrote that most of the extra cost would have been in the original bids had the plans shown that wall from the start.
Where the money would go
The staff report breaks the $24,278,257 increase down this way:
| Item | Increase |
|---|---|
| Building the new retaining wall | $15,975,364 |
| Extra right of way and utilities | $5,000,000 |
| Paid delay, 133 days | $2,402,893 |
| Extra oversight by consultants, county and VDOT staff | $500,000 |
| Potential contingency items | $400,000 |
The right-of-way increase covers three commercial certificates of take and a duct bank, the report says.
The wall change order itself is $18,378,257, which would take Lane’s contract to $79,784,958. The draft change order attached to the report gives slightly lower figures: $17,905,414 for the change and $79,416,529 for the new contract total.
The new finish date
The draft change order adds 163 days to the contract. Completion would move from March 20, 2028, to Aug. 30, 2028.
The project’s budget before this request was $80,938,103. Almost all of it, $80 million, came from the Northern Virginia Transportation Authority’s local funds. The rest came from county general funds, the Prince William Parkway Transportation Improvement District and $44,670 from Buchanan Partners, the developer of the Quartz District planned beside the intersection.
Where the extra money comes from
The added money would come from the county’s local grantors tax fund. That tax is collected when real estate is sold or transferred in the county. The fund mainly pays for regional and local transit, the report says.
The fund holds $51,039,745. It would drop to $26,761,488 after this transfer. County staff recommend approval.
What it means for you
- Work at the intersection runs longer. If supervisors approve, the contract end date moves to Aug. 30, 2028.
- No new tax. The money comes from a fund the county already holds, not a new levy.
- You can speak at the hearing. The meeting starts at 2 p.m. Tuesday at 1 County Complex Court. To comment remotely, register through the county’s SpeakUp! Prince William system by 5 p.m. Monday, Nov. 30, the meeting agenda says.