VDOT is studying whether the reversible I-95 Express Lanes could run both ways at all hours. Public meetings are planned for 2027 and 2028, with no timeline yet.
The Virginia Department of Transportation is studying whether the I-95 Express Lanes could run in both directions at all hours. Today the lanes carry traffic one way at a time, so drivers heading the other way cannot use them.
VDOT presented the idea to the Prince William Board of County Supervisors at its Oct. 20 meeting, the county said in a release. The project is at the feasibility stage. Nothing has been approved, and there is no construction date.
What VDOT is looking at
The study covers about 45 miles of the express lanes, from near the Springfield Interchange in Fairfax County to Spotsylvania County. Under the concept shown to the board:
- three express lanes each way would run from the Franconia-Springfield Parkway area to Prince William Parkway
- two express lanes each way would run south of Prince William Parkway
- the two-way lanes would extend about 10 miles south of U.S. 17
- reversible ramps would be modified or replaced where needed, with access improvements
Prince William Parkway, the road that runs through Lake Ridge, is where the concept drops from three lanes each way to two.
The county said the study will also weigh the effect on OmniRide. Its commuter buses save time when they travel the same way as the express lanes. Buses going the other way have to use the regular lanes.
What is still unknown
The county said feasibility has not been decided because several effects need more study:
- property
- traffic
- road layout
- ramps on and off the lanes
- the environment
The schedule also depends on the study, the approvals it needs and a commercial agreement. The county release did not say who the agreement would be with.
VDOT is collecting field data and doing early engineering and environmental work. A preliminary assessment found much of the work could fit within land the state already owns. Some property may have to be bought in places, and VDOT said its goal is to keep that to a minimum, according to the county.
When the public gets a say
The presentation set out this timeline:
| When | What |
|---|---|
| 2026 | Field data, preliminary engineering and environmental studies |
| 2027 and 2028 | Public information meetings |
| 2028 | Public hearing |
No meeting dates have been set. The presentation is posted on the Board of County Supervisors page.
What it means for you
- Nothing changes yet. The express lanes keep their one-way schedule while the study runs.
- A reverse commute could get a fast lane. If the plan goes ahead, a Lake Ridge driver heading south in the morning or north in the evening would no longer be shut out of the express lanes.
- Ramps near home could change. The concept includes replacing reversible ramps, but the county release did not say which ones.
- Bus riders should watch the OmniRide review. Our story on OmniRide’s proposed Route 94 changes covers the January service plan, and our getting around guide lists the commuter routes.
- Current closures on I-95 and local roads are on our road construction and closures page.
Have your say